MEP subcontractors ask for “a Revit model” and then discover the model cannot be fabricated from. The difference is the level of development. LOD 300 and LOD 400 answer different questions, and paying for 400 on a job that only needs coordination wastes the fee.
LOD 300 is for coordination
An LOD 300 MEP model shows the size, shape, location, and system of the major equipment, mains, and branches. Duct and pipe are accurate enough to clash against structure, architecture, and the other trades. Clearances for access and valves are modeled where the coordination meetings depend on them.
It is the right model for design development, permit support, and trade coordination in Navisworks. It is not a spool drawing. Hangers, specific joint types, and the exact coupling a fabricator orders are usually still generic. Quantities from this model are suitable for budgeting, not for a purchase order.
LOD 400 is for fabrication
LOD 400 adds the detail a shop can build from. That includes fabrication parts or equivalent content, hanger and support strategy where it affects clearance, specified valves and fittings, and routing that accounts for installation, not just the design line. Sheets from this model are shop drawings: dimensions, elevations, tags, and spool breaks.
The inputs change too. LOD 400 needs the approved equipment submittals, the specification, the coordination sign-off, and the fabricator’s standards. Modeling 400 from a schematic PDF produces a precise model of an unapproved design.
What to buy for a typical subcontract
If the architect or engineer still owns the design, start at LOD 300 and run clash detection before anyone fabricates. Move the coordinated areas to LOD 400 only after equipment is selected. Mechanical rooms, riser shafts, and congested corridors are the usual places where 400 pays for itself. Open floor plate with a single main often stays at 300.
Say which systems are in the higher level: supply and return duct, hydronic piping, domestic water and waste, fire protection, conduit, or cable tray. “All MEP at 400” on a hospital is a different job from mains-only 300 on a warehouse.
RevitMart builds both. The Revit MEP drafting scope states the level before modeling starts, so the fee matches the drawings you can actually issue.